One of five wind turbine foundations
completed
fall 2010 on Fire Island.

Timeline


Fall 2011

  • Close construction financing
  • Shoreside transmission work begins

April 2012

  • Mobilize to the island
  • Start on-island construction

July 2012

  • Wind turbines become operational

September 2012

  • First power generated
  • Project commissioning